SMI, Ltd. Home Page > Typical Results
 

Typical Results 

Network Procurement®:  Recurring lead time reduction from multiple weeks to typically less than one week.  Cut prices by up to 30% effective immediately and including long term contracts, with savings typically effective immediately.  Improved quality of delivery, obtained commitment to replace defective deliverables in 48 hours or less, and obtained addition pledges to work to reduce costs an additional 10% by the end of the first year of the contract.  This achievement was the primary reason in the company involved for increasing margins from 18 to 39%, achieving a profit and "saving" the company from a distress sale.

 

Electronics manufacturing:  inventory cut 29% in three months; 30% reduction in purchase prices by the end of the first year; "Team Quality" program which bolstered morale, improved productivity and increased sales.

Development and implementation of a distribution planning and control system for a $100MM per year European industrial and consumer goods manufacturer, resulting in a 35% reduction in finished goods inventory and a 90% improvement in customer service.

Implementation of inter-plant pull signals and a "focused factory" concept for the movement of work-in-process and unassembled stock among four plants of an international industrial goods manufacturer.

 

Pull Signals implementation among a supplier / client firm network of 8 plants located in the Pacific Rim within a 10,000 mile circle and employing over 13,000 personnel.  Reduced affected inventories 25% in the first month of implementation.  Went on to establish inventory controls in support of the inventory reducing / cash flow improvement objective.

 

Setup / Changeover Time Reduction efforts in a large American machinery house resulting in changeover time reductions averaging 70%.  Initiated, trained, and coordinated employee teams to implement the changes required to "institutionalize" the reduced changeover times.

 

 Network Procurement® in Europe:  achieving an 18% immediate cost reduction; reduction of delivery lead times to 1 week or less (down from up to 22 weeks); quality improvements and additional  Continuous Improvement program cost reductions of 9% (first year) and 11% (second year).

  

Implementation of computerized forecasting, sales, and order entry in the multi-warehouse distribution environment for a $100MM per year industrial goods supplier

Implementation of a plant-wide scheduling pull signals system to be used in conjunction with the computerized finite scheduling system in an 800-man aerospace engine prototype facility.  Lead times and WIP inventory cut 65% in five months.

 

Reorganization for flow and flexibility of a 300,000 square foot manufacturing facility (including screw machines, punch presses, molding, winding, and electronic assembly) for a $60MM per year capital equipment producer.  Space requirements cut 40% in 7 months.

 

Recruiting and staffing the management team to position a $40MM high-tech electronics company for rapid growth.  Provided interim management support for over a year while establishing the new team.

 

Selection analysis, negotiating for best (mutual) contract, and implementation of a variety of "MRP II" software packages, including interfacing with all functions.

 

Project development and management for the implementation of closed-loop MRP II in a multi-plant environment, integrated with our previously implemented inter-plant scheduling system.

 

Implementation of a "Production=Sales" planning and scheduling system, from raw material procurement to finished goods shipment, for a Canadian consumer electrical goods manufacturer, resulting in a 60% inventory and lead time reduction and a 99% customer service level.

  



© 2007, 2008, 2009 Synchronous Management International, Ltd.  All rights reserved.

Network Procurement® and Synchronous Management Logos are registered trademarks of Synchronous Management Sarasota, Inc. These trademarks and logos are used by Synchronous Management International, Ltd. with permission of Synchronous Management Sarasota, Inc.